Luca Mining completes Tahuehueto mine

Luca Mining Corp. has completed construction of its Tahuehueto underground operation in Durango State, Mexico. The gold mine has a 1,000-tonne-per-day nameplate processing capacity. “We are extremely pleased with our progress at the Tahuehueto gold mine. Processing rates are currently averaging 450 [t/d] and we expect to steadily increase over the coming weeks to reach commercial production in September 2024,”…

Read More

Tahuehueto approaches final commissioning: Luca Mining

Canadian-based, Mexico-focused Luca Mining said testing of the final equipment to complete construction of its Tahuehueto underground gold mine is almost finished.  In the crushing circuit, a new vibrating screen is currently being installed, to further improve crusher system availability. Additionally, final alignment and testing of the second 750-tonnes-per-day ball mill will be completed this month, providing an installed grinding…

Read More